Four central enterprises settled in Guangyuan, and the installed capacity of wind power generation exceeded 800,000 kilowatts.
Previous survey data show that Guangyuan City is poor in wind energy resources.
byAt the end of December, 2021, four central enterprises "grabbed the wind" in Guangyuan, with a total investment of nearly 7 billion yuan and a total installed capacity of over 810,000 kilowatts.
During the "14th Five-Year Plan" period, the complementary development of water and scenery was carried out, and a "Tingzikou-Baozhu Temple" project was rebuilt.
The river is surging, the wind is leisurely, the sun is scorching, the water and scenery are in full swing, and Guangyuan is developing green energy."the horse is whipped and not saddled."
The mountains are continuous and towering. From a distance, it looks like a fan impeller with fairy dancing sleeves, but it looks like a monster at close range. In the sun, a breeze turns with silver leaves, converting wind energy into electricity.
Time returnAt 19: 09 on December 16th, 2014, a special honor was awarded to Guangyuan-the first mountain wind power generation in Sichuan Province was sent from Datang Fangdiping Wind Farm. Guangyuan wind power generation, Datang Group became the first person to eat crabs. In December 2011, Fangdiping Wind Power Project with an installed capacity of 30,000 kilowatts obtained the "birth certificate". Ten years later, in June 2021, Datang Group invested a total of 2.892 billion yuan and successively built five wind farms in Guangyuan, including Wangjiangping, Liangshuiquan, Hejiashan and Luoquanyan, with a total installed capacity of 320,000 kilowatts.
A stone stirs up a thousand waves. The news that Datang Group entered the field of Guangyuan wind power spread like wildfire, and the central enterprises China Guangdong Nuclear Power Corporation, China Energy Conservation Corporation and China Power Construction Corporation, which smelled good opportunities for development, rushed to the Guangyuan wind power market.By the end of December 2021, four central enterprises had invested a total of 6.823 billion yuan, with a total installed capacity of 819,200 kilowatts, and built 10 wind farms.
"From January to June this year, Fangdiping Power Plant sent out 20.72 million kWh." Dang Zhehui, chief engineer of Datang Sichuan Power Generation Co., Ltd. New Energy Branch, told reporters about the "transcripts" in the first half of the year. The reporter learned from the municipal development and reform that in the first half of the year, the city sent 748.62 million kwh of wind power, equivalent to saving 92,000 tons of standard coal and reducing 746,400 tons of carbon dioxide.
The development and utilization of green energy such as wind power has significantly optimized the production structure of primary energy in the city. till/extremelyBy the end of 2020, wind power and natural gas increased substantially, with average annual growth rates of 74.64% and 56.71% respectively. The speed of coal production slowed down, with an average annual decrease of 19.75%.
At present, Guangyuan’s installed wind power ranks second in the province. Turning the advantage of wind energy resources into the advantage of green development, Guangyuan seized the opportunity.
"The west wind on the river makes a jolt at night" (Ming Yang Shen’s "On Jialing River"), this "jolt" wind has been blowing for hundreds of years and has been blowing until now. Today’s Guangyuan, the wind is famous, but it can tell the male from the female. The sound of "hoo-hoo-hoo" is a "public wind"; The sound of "Ho-ho-ho-ho" is the "mother wind". The "public wind" can uproot the towering trees, and the "mother wind" can blow the yellow leaves out of the clouds. The champion used a word "Dian" to depict the soul of the wind; Ordinary people use "male and female" to describe the shape of the wind. There are also folk songs: the wind in Guangyuan, the onion in Zhaohua.
From the geographical point of view: Guangyuan is located in the north of Sichuan Basin, at the southern foot of Qinling Mountains and at the exit of Jialing River Valley.Under the action of "gorge tube effect", the airflow accelerates through the canyon, and the wind speed increases accordingly, forming more wind energy than the nearby areas. Whether it is historical records, folk proverbs or geographical space, Guangyuan is "the wind is roaring". But who had expected that when wind power was to be developed, Guangyuan was actually a wind-poor area, and wind energy had no development value.
This assertion is not groundless, but comes from the existing satellite survey data. Our city is poor in wind energy resources, so it isIn the demonstration opinion of the province’s wind energy resources planning issued in 2007, our city is not included in the detailed exploration area of the provincial planning, so it cannot be developed and constructed.
Is the historical record wrong? Can’t the good geographical location of our city generate wind energy? surely it doesn’t mean that…/could it be said that…….. Complaints can’t change the status quo, only science can overcome fallacies.
In recent years, the Municipal Development and Reform Commission, with the support of Chaotian District, Municipal Meteorological Bureau, Municipal Science and Technology Bureau and other departments, invited experts and scholars from Jiangsu Branch of China Wind Power Association, China Wind Power Company, Datang New Energy Company and Northwest Electric Power Design Institute to conduct field research and field survey on the city’s wind energy resources, and set up two.10m anemometer tower. After more than a year of data collection, it is estimated that the theoretical development of wind energy is above 2.6 million kilowatts. Experts believe that our city is not only an area rich in wind energy resources, but also has high development and utilization value.
selfIn December 2011, the first wind farm in our city, Fangdiping, was approved for construction. Ten wind farms have been developed and built in the past ten years.
The leaves are long and the wind is not over.
At present, the development of wind power in Guangyuan is imminent. Following the completion of wind power projects in Chaotian District, Lizhou District, Zhaohua District and Jiange County, our city has recently been newly approved by the Provincial Development and Reform Commission and the Provincial Energy Bureau.Seven, with a total investment of 4.096 billion yuan and an installed capacity of 632,200 kilowatts. The investment and distribution areas of the projects are: 3 projects in Zhaohua District, with a total investment of 2.018 billion yuan and an installed capacity of 302,200 kilowatts, including 147,400 kilowatts in Phase II, 72,000 kilowatts in Phase III and 82,800 kilowatts in Phase IV of China Power Construction Baiguo Wind Power; There are 4 projects in Jiange County, with a total investment of 2.078 billion yuan and an installed capacity of 330,000 kilowatts, including 100,000 kilowatts of Tiantai Mountain Phase III, 30,000 kilowatts of Zhongguang Nuclear Bowl Spring, 100,000 kilowatts of Ximiao and 100,000 kilowatts of Guangping.
Wind power development is in the ascendant, and good news comes from the Municipal Development and Reform Commission.—— The Preliminary Implementation Plan for the Water and Scenery Complementary Development Project in the 14th Five-Year Plan of Guangyuan City (hereinafter referred to as the Implementation Plan) has been evaluated by an expert group organized by the Provincial Energy Bureau in conjunction with the Provincial Engineering Consulting and Research Institute.
The minutes of the evaluation meeting of the expert group pointed out that the Implementation Plan conforms to the overall requirements of the national clean energy development and the relevant national and provincial development policies and regulations, and the construction management content has a positive role in promoting the development of local photovoltaic and wind power in an orderly manner. Total installed capacity of the implementation plan project2.179 million kilowatts, with an estimated total investment of 12.3 billion yuan. Relying on Tingzikou Power Station and Baozhusi Power Station, the wind power and photovoltaic resources in a certain range of the two power stations will be sent out by using the existing power grids of the hydropower stations. "During the Tenth Five-Year Plan period, it is planned to build an installed capacity of 1.779 million kilowatts with an estimated total investment of 10.3 billion yuan. Implement and rebuild a’ Tingzikou-Baozhu Temple’ project. " Peng Shiyang, director of the Municipal Development and Reform Commission, said with confidence.
Silver leaves are shining on the top of the mountains, and Guangyuan wind energy blows into the homes of ordinary people!
Fang floor, Guangyuan wind power generation"Elder". Since the power generation in December 2014, by July 2, 2022, a total of 397 million kWh has been generated.
On July 2, the reporter climbed to Fangdiping, the former northwest township of Chaotian District, a mountain at an altitude of 1,500 meters, and listened to the story of the wind farm told by the builder.
The mountain is named Fang terrace, and the wind farm is also named Fang terrace. High tower20 wind turbines, 70 meters long and 89 meters long, stand on the ridge surrounded by clouds and fog in turn. When the blades turn, wind energy is converted into electric energy. Facing a reporter with a blank face, Dang Zhehui, chief engineer of the new energy branch of Datang Sichuan Power Generation Co., Ltd., "dispelled doubts" to the reporter.
Mountain breeze blows the impeller of the fan, which drives the generator to convert wind energy into electromagnetic induction.690 volts of electricity. The wind turbine box transformer boosts the electric energy of 690 V to 35 kV, and then it is sent to the Fangdiping booster station through the power collection line, and then it is boosted to 110 kV by the main transformer, and sent to the Mingyuexia Substation of the State Grid to enter the Sichuan power grid.
A wisp of breeze in the forest, that’s all."Butterfly changes" the electricity that adults need for food, clothing, housing and transportation, and industrial agriculture.
Since it was put into production, Fangdi floor fan has been running safely for nearly three years.Eight years. In the past eight years, China’s manufacturing industry has undergone earth-shaking changes. In order to monitor the operation parameters of wind turbines, Fangdiping Wind Farm has built a central control room. Now, Datang Sichuan New Energy has built a more advanced central control room in Chengdu-fans and photovoltaics that can centrally monitor the electric fields in Guangyuan, Liangshan and Ganzi. Therefore, the central control room of Fangdiping Wind Farm has completed its historical mission and no longer undertakes monitoring tasks. Wu Yingang, deputy stationmaster of Guangyuan Operation and Maintenance Station of Datang Sichuan New Energy Branch, told the reporter that in order to keep pace with the times, it was decided to carry out technical transformation on the fan.
Installed capacity of Fangdiping wind farm30,000 kilowatts, consisting of 20 1500-watt fans. This transformation will extend the diameter of the wind wheel from 89 meters to 1.5 meters, reaching 90.5 meters. After the technical transformation is completed, the utilization rate of wind energy will increase by more than 5%. After the technical transformation, the wind farm will dance in the mountains with a brand-new attitude.
Zhang Jiaming is a security officer of Fangdiping Wind Farm, and he is from Lizhou District.Worked in January 2016.
Attending the pre-class meeting is Zhang Jiaming every day.The main content of the pre-class meeting is "three stresses and one implementation" According to the assigned tasks, Zhang Jiaming went to the wind farm to carry out maintenance work.
Zhang Jiaming said that when he first joined the work, the road conditions of Fangdiping Wind Farm were poor, and he patrolled the collector lines, so he had to walk where the vehicles could not reach. Shuttle through the mountains, walk every day.8 kilometers. "Sometimes there are snakes." Seeing the reporter’s surprise, the young man disagreed: "In fact, I am not afraid."
Nowadays, it’s all cement roads, and patrolling the mountains (referring to patrolling the collecting lines) is all about driving and patrolling in one day.More than 20 kilometers, no need to walk.
Dang Zhehui added that the change is not only the car patrol, but also the digital wisdom upgrade of Fangdiping Wind Farm, which improves the labor productivity of all employees and the happiness index of employees.
Guangyuan wind power generation can be described as from scratch, from existence to strength!
This change is inseparable from the project.
The first is to continue to strive for projects. Initially, experts believed that Guangyuan did not have the conditions for wind power development. Later, Fangdiping wind power project was approved.
Today, Guangyuan hasThere are 10 wind farms with an installed capacity of nearly 820,000 kilowatts, which is larger than Baozhusi Power Station. The achievement of these achievements is the result of continuing to strive for the project. Winning the project is bound to encounter all kinds of difficulties. In the face of difficulties, if you flinch, the difficulties will become bigger and bigger. In the face of difficulties, if you go forward bravely, difficulties will be trampled underfoot. In terms of winning projects, Guangyuan people took the initiative and enterprising spirit to reach the goal, and finally won 10 wind power projects. In the face of achievements, Guangyuan people are not satisfied, but continue to strive for projects. Hard work pays off, and Guangyuan has won seven wind power projects with a total investment of over 4 billion yuan.
The second is to promote projects with high efficiency. To land the hard-won project, we must build it well. In recent years, Guangyuan has continued to carry out project year activities, continue to fight on wall charts, and continue to carry out project training and evaluation. There are fewer difficulties to talk about, and there are more ways to promote projects. In the hot construction, wind power projects have changed from blueprints to wind farms. Project construction, love to fight will win.
Once again, it is to operate the project well. People often say that projects"Trilogy": recruit, build and turn. No matter how good the project is, if it can’t be turned around, it will be unsustainable. Therefore, it is very important to run the project well. The Baiguo wind power project, which was completed at the end of December last year, received 95.62 million kWh of electricity in the first half of this year, achieving the scheduled goal. To run the project well, apart from relying on professional talents, it is more important for the local government to provide a good business environment. At present, Guangyuan is making efforts to create the best business environment in Sichuan, that is, to make the enterprises generated by the project focus on development. Only when the enterprise operates smoothly can it gradually recover its previous investment. Only in this way can the investment, construction and operation of enterprises enter a virtuous circle, and enterprises can have more confidence in project investment.
The construction history of Guangyuan wind power project proves that the project construction in our city is stable and far-reaching.